England & Scotland Glasgow · Aberdeen · Fareham
Operatives working from a boom lift against precast concrete substation walls

Recent Projects

Case studies from substations, grid stability plants and specialist packages across England and Scotland.

Case studies

Grid supply points and transmission substations

A selection of recent PKBC packages for tier-1 main contractors and energy developers, starting with internal fit-out on new transmission infrastructure for SSEN.

Gremista Grid Supply Point 132kV Substation, Shetland

Client
SSEN
Main contractor
Morgan Sindall
Location
Gremista, Shetland

PKBC delivered the complete internal fit-out of the new grid supply point serving the Shetland HVDC link. The package covered system scaffold, blockwork, drylining and joinery, timber and suspended grid ceilings, a kitchen, fire doors with ironmongery, and painting, spraying and taping, including acid-resistant and anti-slip coatings.

PKBC operative installing suspended-ceiling services from a scissor lift inside the Gremista substation building

Kintore 132kV Substation, Phase 3

Client
SSEN
Main contractor
OMEXOM
Location
Kintore, Aberdeenshire

On Phase 3 of the Kintore substation we delivered all internal fit-out works: system scaffold, blockwork, drylining and joinery, timber and suspended grid ceilings, a kitchen, fire doors with ironmongery, painting, spraying and taping, and firestopping and fireproofing.

Blocklaying from scaffold towers inside a steel-framed substation building

Grid stability and synchronous condensers

Construction packages on the plants that keep the grid stable as renewable generation grows.

Thurso Synchronous Condenser, 400kV Transmission Substation

Client
Welsh Power
Main contractor
RJ McLeod
Location
Thurso, Caithness

At the Thurso synchronous condenser substation PKBC carried out additional works packages, including the application of anti-slip floor paint to all floors of the facility.

PKBC operative carrying out floor-coating works at the Thurso synchronous condenser substation

Gretna Grid Stability Plant, 275kV Substation

Client
Welsh Power
Main contractor
TSK and RJ McLeod
Location
Gretna, Dumfries and Galloway

At the Gretna grid stability plant on the border we completed requested works packages, including final grouting of the external fire wall and firestopping and fireproofing.

Fire-stopped and labelled cable penetrations in a cable trench

400kV substations

Fit-out and additional works on 400kV sites in England and Scotland.

Eye Synchronous Condenser, 400kV Grid Stability Facility

Client
Conrad Energy
Main contractor
ACS and Siemens Energy
Location
Eye, Suffolk

At the Eye grid stability facility in the east of England PKBC carried out additional works, including the supply and installation of fire doors and painting works.

PKBC operative passing through newly installed fire doors marked Danger of Death at the Eye grid stability facility

Beatrice 400/220kV Substation, Blackhillock

Client
TINZ
Main contractor
RJ McLeod
Location
Blackhillock, Moray

PKBC delivered the full internal fit-out for the Beatrice substation at Blackhillock: blockwork, drylining and joinery, timber and MF suspended ceilings, fire doors with ironmongery, painting, spraying and taping including acid-resistant and anti-slip coatings, raised access floors, and firestopping and fireproofing.

Raised access floor and open service bays inside the Beatrice substation building

Live substations

Renovation and repair inside operational SSEN substations, delivered under live-site permits and controls.

Lochay 132kV Live Substation, Existing Building

Client
SSEN
Main contractor
Global Infrastructure

Working inside a live, operational substation, PKBC renovated the existing Lochay building: demolition works, stripping and replacement of the old high-level timber ceiling, painting and taping including acid-resistant coatings, and the design and installation of fire doors with ironmongery.

PKBC operatives working from a podium inside the existing substation building

Beauly 132kV Substation, Existing Building

Client
SSEN
Main contractor
Global Infrastructure
Location
Beauly, Highland

At the existing part of the live Beauly substation we carried out repair works, including stripping and replacement of the reveals to the external steel fire doors, together with painting works.

Steel fire door installed in the existing substation building

New substation buildings

New-build packages, from full internal fit-out to a design and build main contract.

Lochay 132kV Substation, New Building

Client
SSEN
Main contractor
Global Infrastructure

Alongside the renovation of the existing building, PKBC delivered the complete internal fit-out of the new Lochay substation building: drylining and joinery, MF suspended ceilings, a kitchen, fire doors with ironmongery, painting, spraying and taping including acid-resistant coatings, and firestopping and fireproofing.

Spray painting the blockwork interior of the new substation building

Kelvin ERF 44MW Substation

Client
Western Power
Main contractor
Acciona
Location
West Bromwich, West Midlands

Kelvin is a 44MW waste-to-energy facility in West Bromwich. PKBC undertook a design and build main contract for one of the buildings, covering system scaffold, brickwork and METSEC installation, drylining and joinery, MF suspended ceilings, external steel fire doors, mechanical and electrical works, plumbing, painting and taping, and roofing.

METSEC framing and sheathing under way on the new building

Distilleries and other work

Specialist packages beyond the energy sector, at home and abroad.

Glenglassaugh Distillery

Client
Brown-Forman
Main contractor
Luddon Construction
Location
Aberdeenshire

For a whisky warehouse at Glenglassaugh Distillery, PKBC installed over 1,000 square metres of system scaffold and built over 1,000 square metres of concrete block walls, then painted the walls, applied floor line marking and carried out diamond core drilling.

Blockwork walls and multi-lift scaffold inside the whisky warehouse

Biohacking Studio, Switzerland

Client
Private client
Location
Switzerland

PKBC delivered the complete internal fit-out of this overseas project in Switzerland: drylining and joinery, kitchen and furniture installation, door installation, painting, spraying and taping, and flooring.

Plastered walls with arched niches during the studio fit-out

Where we have worked

24 project sites across the UK, from Shetland to the south coast, on one interactive map.

View the projects map

Have a package to price?

Send us your scope and drawings. We price civil works and specialist packages across England and Scotland.

Discuss a project